St. Louis Park Fire

Total Project $305,613.53

The URI Difference

Project Budget

Original Offer: $138,436.53

Final Offer: $305,613.53

Added Value: $167,177 (54.70%)

Project Overview

  • Ultimate Restoration’s final agreed upon estimate with insurance company was $305,613.53. The original estimate from the insurance company first estimate was $138,43.53 That’s an additional $167,176.57 or 54% of value recovered by URI!
  • Insurance Company stated maximum payout would be $260,000.00 coverage A amount. URI was able to find additional coverage & get the insurance company to pay an additional $45,613.53 in additional coverage.
  • The Homeowner made open floor plan changes. The new floor plan did not cost the Homeowner anything.