Total Project $228,238.31

The URI Difference

Project Budget

Original Offer: $121,834.66

Final Offer: $228,238.31

Added Value: $106,403.65 (46.62%)

Project Overview

  • Ultimate Restoration’s final agreed upon estimate with the insurance company was $228,238.31. Benchmark Building Consultant LLC was hired by the insurance company to get the agreed upon estimate secured on the Insurance Companies behalf. Their first estimate was $121,834.66. That’s an additional $106,403.65 or 46% of value put into this project which was recovered by URI!
  • Project was completed in 3 1/2 months because URI never takes a work day off!
  • Ultimate Restoration completed all the repairs staying with in all budgets. Homeowner paid nothing out of pocket.