URI Logo

Minneapolis Fire

Total Project $432,139.45

The URI Difference

Project Budget

Original Offer: $165,010.1

Final Offer: $432,139.45

Added Value: $267,129.35 (61.82%)

Project Overview

  • Ultimate Restoration’s final agreed upon estimate with the Insurance Company was $432,139.45. The original insurance company estimate was $165,010.10. Insured only had $338,874.94 in coverage. URI worked with the client to get the repairs completed within the insurance coverage amount!
  • URI helped owner design new space and make multiple changes to the property.
  • The project was completed in 5 ½ months because URI never takes a workday off.

Before & After Photos